Hello,
After submitting a quote to a customer from CRM online, when customer response is positive then we can start working on his project and for that we validate the Quote as Won, which then create a customer Order reference with which we can settle different task to be done for the project.
In our business we are building software and on current customer order we need to track the number of hours spend on the project by each people working on it.
To do that actually we are using an Excell sheet that each developer working on the project fill up weekly. Which is not the best solution as it is not directly linke to customer order in CRm.
I was wondering if there is a way to do such thing in the sense that from customer Order we can fill up a date, developer name, number of hours spend ?
At the end we can then compare the payed hours with real working one.
Thanks for advise
regards
serge