Schedule Work Order for more than one day in the Schedule Board

$
0
0

When scheduling a resource to work on a Work Order I cannot find a way to automatically split the WO duration in open hours of the Resource calendar. I.E. A resource has a calendar for normal work 8 hours per day. The WO duration is 24 hours. Is there a way to have the Bookable Resource Booking made to the open hourds of the calendar? Instead of having all 24 hours booked on the same day they should be planned over 3 days. 

Any ideas?

Thanks

Gunnar